Upgrading S7-400H CPU 417-4H to CPU 410-5H with F-Safety: Backplane Compatibility, Fiber Sync, and SEC Sizing
Yes, existing S7-400H backplane racks (such as UR2-H or dual UR1/UR2 racks) can be 100% reused when upgrading an AS 417-4H to a CPU 410-5H with F-Safety in SIMATIC PCS 7 V8.2. Safety operation does not mandate rack replacement. However, three critical hardware and licensing changes are mandatory: the existing optical sync submodules must be replaced with CPU 410-specific sync submodules (6ES7960-1AA08-0XA0), each CPU 410-5H requires a dedicated System Expansion Card (SEC) sized to the facility's required Process Object (PO) count (e.g., 6ES7653-2BA00-0XB0 for 2,600+ PO), and a separate Safety Matrix / F-Runtime license must be provisioned.
Table of Contents
- Hardware Migration Strategy: Replacing CPU 417-4H with CPU 410-5H
- Backplane Compatibility: Reusing UR2-H and UR1/UR2 Racks
- Mandatory Hardware Replacements: Sync Submodules and Power Supplies
- System Expansion Card (SEC) Sizing and Licensing Guardrails
- CPU 417-4H vs CPU 410-5H Technical and Architecture Comparison
- Verification
- Limitations and Operational Precautions
- Engineer FAQ
- Technical References
- Related Articles
- Related Tags
Hardware Migration Strategy: Replacing CPU 417-4H with CPU 410-5H
Facilities running mature SIMATIC PCS 7 systems frequently hit memory and performance limits on older S7-400H controllers (such as CPU 417-4H 6ES7417-4HT14-0AB0 or 6ES7417-4XT05-0AB0). When upgrading to PCS 7 V8.2 or V9.x, the SIMATIC PCS 7 CPU 410-5H Process Automation (6ES7410-5HX08-0AB0) serves as the universal replacement.
Engineers facing tight turnaround outages often ask whether the existing physical backplane racks can be preserved while performing a rapid CPU swap, particularly when integrating Fail-Safe (F-Safety) functionality.
Backplane Compatibility: Reusing UR2-H and UR1/UR2 Racks
According to the official CPU 410-5H Process Automation System Manual:
-
Full Backplane Compatibility: The CPU 410-5H utilizes the standard S7-400 physical form factor and backplane bus (P-bus and K-bus). It mounts directly into existing UR2-H split redundant racks (
6ES7400-2JA00-0AA0) or dual independent UR1 (6ES7400-1TA01-0AA0) / UR2 (6ES7400-1JA01-0AA0) racks. -
Safety Functionality: Fail-safe operation in PCS 7 (using S7 F-Systems and Safety Matrix) is purely software- and communication-driven (PROFIsafe protocol). Fail-safe operation does not require specialized backplane racks.
Mandatory Hardware Replacements: Sync Submodules and Power Supplies
While the rack and I/O cards can be reused, specific components cannot be transferred from the CPU 417-4H:
- Optical Sync Submodules: The synchronization submodules used on older CPU 417-4H controllers (e.g.,
6ES7960-1AA04-0XA0or6ES7960-1AA06-0XA0) are incompatible with CPU 410-5H. You must install the dedicated CPU 410 sync submodules:
- Short-range up to 10 m:
6ES7960-1AA08-0XA0(requires 2 per CPU, total 4 for a redundant pair). - Long-range up to 10 km:
6ES7960-1AB08-0XA0.
- Power Supply Capacity: The CPU 410-5H consumes higher backplane current during dual PROFINET operation. Ensure existing power supplies (e.g., PS 407 10A
6ES7407-0KA02-0AA0or PS 407 20A) have sufficient capacity margin.
System Expansion Card (SEC) Sizing and Licensing Guardrails
Unlike CPU 417-4H, which used physical RAM/Flash memory cards to expand work memory, the CPU 410-5H features a single, universal hardware CPU where processing capacity is unlocked exclusively via the System Expansion Card (SEC):
-
SEC Mandatory Unit: The CPU 410-5H cannot boot without an SEC inserted. The SEC sets the maximum number of Process Objects (PO) the controller can execute.
-
SEC Sizing Tiers: SECs are available in distinct PO packages: 100 PO, 500 PO, 1,000 PO, 1,600 PO, and 2,600+ PO (PO 2k+).
-
F-Safety Licensing: To enable fail-safe CFC charts, the controller must have an active F-Runtime License (
6ES7653-2CX00-0XB0or6ES7653-2CX01-0XB0). In redundant H-systems, a separate F-license is required for each CPU.
CPU 417-4H vs CPU 410-5H Technical and Architecture Comparison
The following table compares specifications and upgrade requirements between CPU 417-4H and CPU 410-5H:
6ES7960-1AA04/06-0XA06ES7960-1AA08-0XA0Verification
Verify the hardware upgrade through the following steps:
- Insert the SECs and sync submodules into both CPU 410-5H processors. Mount them into the UR2-H rack.
- Connect fiber-optic sync cables crosswise (Upper to Lower, Lower to Upper). Power up the rack.
- Verify that the
RUNLED lights green on Master CPU 0 andRUNlights green on Standby CPU 1 withREDFextinguished. - In SIMATIC Manager HW Config, update the station hardware definition to CPU 410-5H with the correct firmware and SEC PO tier.
- Download the hardware configuration. Open Module Information; confirm that PO utilization is within SEC limits and redundancy coupling indicates 'Redundant mode'.
Limitations and Operational Precautions
Consider these operational rules when upgrading to CPU 410-5H:
-
Never Power Up Without SEC: Attempting to boot a CPU 410-5H without an SEC card inserted causes a persistent DEFECT LED fault; the card must be seated before powering the rack.
-
Fiber Cable Handling: Ensure single-mode vs multi-mode fiber patch cables match the sync submodule optics (standard
6ES7960-1AA08-0XA0uses multi-mode 50/125 µm or 62.5/125 µm duplex cables). -
Commercial Disclaimer: Commercial Accuracy Disclaimer: Software order numbers (MLFBs), package structures, and hardware capacity prerequisites vary across PCS 7 versions and hardware platforms. System integrators must confirm exact software entitlements and licensing requirements against the official Siemens Catalog CA 01 and obtain an authorized Siemens distributor quotation prior to purchasing.
Engineer FAQ
What is the function of the System Expansion Card (SEC) on CPU 410-5H?
The SEC is a hardware security token that defines the maximum number of Process Objects (PO) the CPU 410-5H is authorized to execute in the AS.
Can PO capacity be expanded on CPU 410-5H without replacing the SEC?
Yes, by purchasing an online SEC PO upgrade package and applying the activation code via SIMATIC Management Console without stopping the CPU.
Can I keep my existing S7-400 I/O cards in the same rack with CPU 410-5H?
Yes, standard S7-400 central I/O cards and communication coprocessors (CP 443-1, CP 441) are fully supported in the rack alongside CPU 410-5H.
Technical References
- SIMATIC Process Control System PCS 7 CPU 410-5H Process Automation Manual (Entry ID: 109780813)
- SIMATIC Fault-Tolerant Systems S7-400H System Manual
- SIMATIC S7 F/FH Systems - Configuring and Programming Manual
- Siemens Industry Mall: CPU 410-5H System Expansion Card Sizing and Configurator
Related Articles
- CPU 410-5H System Expansion Card Online Process Object Upgrades
- Hardware Architecture and Failsafe Product Selection for Redundant Safety Systems
- S7-400 CPU 417-4 Spare Part Compatibility in SIMATIC PCS 7
Related Tags
- CPU 410-5H
- AS 417-4H
- Hardware Upgrade
- UR2-H Backplane
- Sync Submodules
- SEC Sizing